Makedonia Palace is a five star hotel in Thessaloniki. In
44 days time, 4 elevators of 10 stops each (visitors) were
dismantled and 4 10-stops mechanical elevators were
constructed and re-installed, with 4-plex operation,
Destination Control system and touch controls for floors
and cabins. At the same time, an additional 6 elevators
were partially renovated in the hotel complex.
4 ELEVATORS
10 STOPS
1,6 M/S
4-PLEX with
DESTINATION CONTROL
Photo Gallery
More projects

PRIMARY PUBLIC SCHOOL
PRIMARY PUBLIC SCHOOL JASTRZEBIE ZDROJ, POLAND A 4-stop Hydro elevator with a capacity of 800kg was installed in the PrimaryPublic School of Jastrzebie Zdroj, in

HOTEL
HOTEL THESSALONIKI GREECE In one of the best hotels in Northern Greece, Wyltor installed 1 panoramicelevator with a maximum weight of 1125kg, 1 hydraulic elevator

COMPLEX LAZARET
COMPLEX LAZARET HERCEG NOVI, MONTENEGRO Complex Lazaret is an adaptive reuse of an old 18th Century Venitian Lazaret.This architectural complex consists of two parts: a

STADIUM
STADIUM SYDNEY, AUSTRALIA Positioned overlooking the Pacific Ocean, in Wollongong (Sydney), and venuecapacity 22.000, this stadium is designed as a multi-purpose facility with theability to

CITY HALL
CITY HALL POLYGYROS, GREECE The installation of an elevator in this project was a special case, as there wasno space predicted in the historic building,

RESIDENTIAL BUILDING
LUXURY RESIDENTIAL COMPLEX THESSALONIKI, GREECE 6-stop MRL elevator with a maximum load up to 630 kg, were installed in thefacilities of a luxury residential complex.